Home > Research > Publications & Outputs > Workload control: Successful implementation tak...
View graph of relations

Workload control: Successful implementation taking a contingency-based view of production planning & control

Research output: Contribution to Journal/MagazineJournal articlepeer-review

Published

Standard

Workload control: Successful implementation taking a contingency-based view of production planning & control. / Hendry, Linda; Huang, Yuan; Stevenson, Mark.
In: International Journal of Operations and Production Management, Vol. 33, No. 1, 2013, p. 69-103.

Research output: Contribution to Journal/MagazineJournal articlepeer-review

Harvard

APA

Vancouver

Hendry L, Huang Y, Stevenson M. Workload control: Successful implementation taking a contingency-based view of production planning & control. International Journal of Operations and Production Management. 2013;33(1):69-103. doi: 10.1108/01443571311288057

Author

Hendry, Linda ; Huang, Yuan ; Stevenson, Mark. / Workload control: Successful implementation taking a contingency-based view of production planning & control. In: International Journal of Operations and Production Management. 2013 ; Vol. 33, No. 1. pp. 69-103.

Bibtex

@article{18e9cb4046a54e0782da1c79f3136d10,
title = "Workload control: Successful implementation taking a contingency-based view of production planning & control",
abstract = "Purpose – The purpose of this paper is to present a successful implementation of a comprehensive workload control (WLC) concept; and to describe the associated implementation process.Design/methodology/approach – Longitudinal action research using a contingency-based approach to ensure alignment between the case company and the characteristics of the WLC approach; and the resulting expected improvements in performance. A set of 17 issues and responses from the literature is used as a checklist for implementing WLC.Findings – Performance improvements include: reduced lead times; significant improvement in lateness and tardiness; reduced costs; improved internal and external co-ordination; and higher quality. The relevance of 15 of the 17 implementation issues is confirmed along with the same response as in previous research for ten issues and an improved response for five issues. In addition, three new issues are identified and addressed.Research limitations/implications – Dependability was a more important competitive priority in this company than speed; and, therefore, the ability of WLC to reduce lead times was not fully assessed.Practical implications – The importance of a contingency-based approach to production planning and control is confirmed. Comprehensive WLC approaches are closely aligned with the high-variety/low-volume context of make-to-order (MTO) companies.Originality/value – This is the first paper that empirically demonstrates performance improvements resulting from WLC alongside a detailed discussion of the implementation process. Few examples of successful implementations have been published previously, and these tend to treat the implementation process as a “black box”. Where more detail on the implementation process has been given in previous studies, evidence of effectiveness in practice was not provided.",
keywords = "Action research, Implementation strategy , Make-to-order , Performance management , Production planning and control , Workload control",
author = "Linda Hendry and Yuan Huang and Mark Stevenson",
year = "2013",
doi = "10.1108/01443571311288057",
language = "English",
volume = "33",
pages = "69--103",
journal = "International Journal of Operations and Production Management",
issn = "0144-3577",
publisher = "Emerald Group Publishing Ltd.",
number = "1",

}

RIS

TY - JOUR

T1 - Workload control: Successful implementation taking a contingency-based view of production planning & control

AU - Hendry, Linda

AU - Huang, Yuan

AU - Stevenson, Mark

PY - 2013

Y1 - 2013

N2 - Purpose – The purpose of this paper is to present a successful implementation of a comprehensive workload control (WLC) concept; and to describe the associated implementation process.Design/methodology/approach – Longitudinal action research using a contingency-based approach to ensure alignment between the case company and the characteristics of the WLC approach; and the resulting expected improvements in performance. A set of 17 issues and responses from the literature is used as a checklist for implementing WLC.Findings – Performance improvements include: reduced lead times; significant improvement in lateness and tardiness; reduced costs; improved internal and external co-ordination; and higher quality. The relevance of 15 of the 17 implementation issues is confirmed along with the same response as in previous research for ten issues and an improved response for five issues. In addition, three new issues are identified and addressed.Research limitations/implications – Dependability was a more important competitive priority in this company than speed; and, therefore, the ability of WLC to reduce lead times was not fully assessed.Practical implications – The importance of a contingency-based approach to production planning and control is confirmed. Comprehensive WLC approaches are closely aligned with the high-variety/low-volume context of make-to-order (MTO) companies.Originality/value – This is the first paper that empirically demonstrates performance improvements resulting from WLC alongside a detailed discussion of the implementation process. Few examples of successful implementations have been published previously, and these tend to treat the implementation process as a “black box”. Where more detail on the implementation process has been given in previous studies, evidence of effectiveness in practice was not provided.

AB - Purpose – The purpose of this paper is to present a successful implementation of a comprehensive workload control (WLC) concept; and to describe the associated implementation process.Design/methodology/approach – Longitudinal action research using a contingency-based approach to ensure alignment between the case company and the characteristics of the WLC approach; and the resulting expected improvements in performance. A set of 17 issues and responses from the literature is used as a checklist for implementing WLC.Findings – Performance improvements include: reduced lead times; significant improvement in lateness and tardiness; reduced costs; improved internal and external co-ordination; and higher quality. The relevance of 15 of the 17 implementation issues is confirmed along with the same response as in previous research for ten issues and an improved response for five issues. In addition, three new issues are identified and addressed.Research limitations/implications – Dependability was a more important competitive priority in this company than speed; and, therefore, the ability of WLC to reduce lead times was not fully assessed.Practical implications – The importance of a contingency-based approach to production planning and control is confirmed. Comprehensive WLC approaches are closely aligned with the high-variety/low-volume context of make-to-order (MTO) companies.Originality/value – This is the first paper that empirically demonstrates performance improvements resulting from WLC alongside a detailed discussion of the implementation process. Few examples of successful implementations have been published previously, and these tend to treat the implementation process as a “black box”. Where more detail on the implementation process has been given in previous studies, evidence of effectiveness in practice was not provided.

KW - Action research

KW - Implementation strategy

KW - Make-to-order

KW - Performance management

KW - Production planning and control

KW - Workload control

U2 - 10.1108/01443571311288057

DO - 10.1108/01443571311288057

M3 - Journal article

VL - 33

SP - 69

EP - 103

JO - International Journal of Operations and Production Management

JF - International Journal of Operations and Production Management

SN - 0144-3577

IS - 1

ER -