Order Release, Dispatching and Resource Assignment in Multiple Resource Constrained Job Shops: An Assessment by Simulation

Research output: Contribution to Journal/MagazineJournal articlepeer-review

Published

Standard

Order Release, Dispatching and Resource Assignment in Multiple Resource Constrained Job Shops: An Assessment by Simulation. / Thurer, Matthias; Stevenson, Mark.
In: International Journal of Production Research, Vol. 60, No. 12, 30.06.2022, p. 3669-3681.

Research output: Contribution to Journal/MagazineJournal articlepeer-review

Harvard

APA

Vancouver

Thurer M, Stevenson M. Order Release, Dispatching and Resource Assignment in Multiple Resource Constrained Job Shops: An Assessment by Simulation. International Journal of Production Research. 2022 Jun 30;60(12):3669-3681. Epub 2021 May 26. doi: 10.1080/00207543.2021.1930240

Author

Bibtex

@article{237a421f0a8d4c259240dd17f998c987,
title = "Order Release, Dispatching and Resource Assignment in Multiple Resource Constrained Job Shops: An Assessment by Simulation",
abstract = "In manufacturing shops in practice, machine capacity is often constrained by more than one type of resource. Yet research mainly focusses on the effects of only one type of resource that constrains machine capacity, e.g. labour, tooling or auxiliary constraints. In response, we use simulation to assess the impact of order release, dispatching and resource assignment rules in make-to-order job shops with multiple resource constraints. The capacity wasted while a machine stands idle waiting for other resources increases with the number of constraints, and all three production planning and control functions have little impact on this waiting time. Effective production planning and control can however improve operational performance in terms of time and tardiness-related measures. In general, combining order release control with a dispatching rule that prioritises jobs for which all resources are available at dispatching and a longest queue resource assignment rule leads to the best performance. Most importantly, and rather counterintuitively, prioritising orders with the fewest missing resources worsens the performance of both the dispatching and resource assignment rule since it reduces resource utilisation during periods of high load. Results from dual resource-constrained shops are consequently not directly transferable to more complex resource-constrained shops.",
keywords = "Theory of constraints, order release, dispatching, resource allocation, workload control",
author = "Matthias Thurer and Mark Stevenson",
note = "This is an Accepted Manuscript of an article published by Taylor & Francis in International Journal of Production Research on 26/05/2021, available online: http://www.tandfonline.com/10.1080/00207543.2021.1930240",
year = "2022",
month = jun,
day = "30",
doi = "10.1080/00207543.2021.1930240",
language = "English",
volume = "60",
pages = "3669--3681",
journal = "International Journal of Production Research",
issn = "0020-7543",
publisher = "Taylor and Francis Ltd.",
number = "12",

}

RIS

TY - JOUR

T1 - Order Release, Dispatching and Resource Assignment in Multiple Resource Constrained Job Shops

T2 - An Assessment by Simulation

AU - Thurer, Matthias

AU - Stevenson, Mark

N1 - This is an Accepted Manuscript of an article published by Taylor & Francis in International Journal of Production Research on 26/05/2021, available online: http://www.tandfonline.com/10.1080/00207543.2021.1930240

PY - 2022/6/30

Y1 - 2022/6/30

N2 - In manufacturing shops in practice, machine capacity is often constrained by more than one type of resource. Yet research mainly focusses on the effects of only one type of resource that constrains machine capacity, e.g. labour, tooling or auxiliary constraints. In response, we use simulation to assess the impact of order release, dispatching and resource assignment rules in make-to-order job shops with multiple resource constraints. The capacity wasted while a machine stands idle waiting for other resources increases with the number of constraints, and all three production planning and control functions have little impact on this waiting time. Effective production planning and control can however improve operational performance in terms of time and tardiness-related measures. In general, combining order release control with a dispatching rule that prioritises jobs for which all resources are available at dispatching and a longest queue resource assignment rule leads to the best performance. Most importantly, and rather counterintuitively, prioritising orders with the fewest missing resources worsens the performance of both the dispatching and resource assignment rule since it reduces resource utilisation during periods of high load. Results from dual resource-constrained shops are consequently not directly transferable to more complex resource-constrained shops.

AB - In manufacturing shops in practice, machine capacity is often constrained by more than one type of resource. Yet research mainly focusses on the effects of only one type of resource that constrains machine capacity, e.g. labour, tooling or auxiliary constraints. In response, we use simulation to assess the impact of order release, dispatching and resource assignment rules in make-to-order job shops with multiple resource constraints. The capacity wasted while a machine stands idle waiting for other resources increases with the number of constraints, and all three production planning and control functions have little impact on this waiting time. Effective production planning and control can however improve operational performance in terms of time and tardiness-related measures. In general, combining order release control with a dispatching rule that prioritises jobs for which all resources are available at dispatching and a longest queue resource assignment rule leads to the best performance. Most importantly, and rather counterintuitively, prioritising orders with the fewest missing resources worsens the performance of both the dispatching and resource assignment rule since it reduces resource utilisation during periods of high load. Results from dual resource-constrained shops are consequently not directly transferable to more complex resource-constrained shops.

KW - Theory of constraints

KW - order release

KW - dispatching

KW - resource allocation

KW - workload control

U2 - 10.1080/00207543.2021.1930240

DO - 10.1080/00207543.2021.1930240

M3 - Journal article

VL - 60

SP - 3669

EP - 3681

JO - International Journal of Production Research

JF - International Journal of Production Research

SN - 0020-7543

IS - 12

ER -